Reykjavik must retender traffic light contract and pay one million krónur

Sunday 22nd November 2026 on 22:15 in Iceland

public procurement, reykjavik, traffic lights

Reykjavik must reopen a procurement for traffic light equipment at two intersections and pay supplier Reykjafell one million krónur in legal costs, mbl.is reported. The Public Procurement Complaints Committee annulled the city’s procurement process and ordered it to advertise the contract across the European Economic Area.

The equipment is intended for the junctions of Snorrabraut with Hverfisgata and with Laugavegur, as part of the first phase of Borgarlína. The city sent requests for quotations to selected companies on July 3. Reykjafell, one of the companies invited, filed a complaint on July 23.

The committee temporarily suspended the process on September 21 while it considered the complaint. Its decision to annul the procurement is dated November 9 and was published on November 20.

Reykjavik argued that special procurement rules for transport services applied, allowing a higher financial threshold. The committee rejected that argument, saying the equipment would control traffic at intersections on the city’s general road network.

In assessing whether the purchase had to be advertised, the committee also considered the city’s regular replacement of traffic light equipment. Purchases of similar equipment totalled 59.1 million krónur, excluding value-added tax, in the 12 months before the city sought quotations. The threshold for municipal goods contracts was 31.9 million krónur, so the committee found that the procurement should have been advertised across the EEA.

Reykjafell had argued that a requirement for the equipment to connect to the city’s central traffic light control system was tailored to equipment made by Yunex Traffic. The committee said the evidence did not support the claim and noted that, according to information from the city that was not disputed, Reykjafell’s equipment had previously connected to the system without problems.

No bids were submitted in the procurement process. The committee therefore found that Reykjafell had not incurred costs preparing a bid or taking part, and rejected the company’s request for an opinion on the city’s liability for damages. It also rejected Reykjafell’s request to declare contracts for purchasing and upgrading central control equipment invalid, because the deadline for challenging those contracts had passed.