Appeals panel upholds contractor’s exclusion from National Hall tender
Wednesday 25th November 2026 on 07:45 in
Iceland
ÞG verktakar was rightly barred from bidding to design and build the National Hall because its nominated steelwork master did not meet the experience requirement, a procurement appeals panel has ruled, according to mbl.is.
The contractor’s application for prequalification named a steelwork master who had not completed two years of experience in that role. It was not yet clear whether the project would require a steelwork master. The day after its application was rejected, ÞG verktakar submitted another person’s master certificate, but the buyer did not allow the company to amend its application.
The appeals panel said the buyer was entitled to reject both the application and the later certificate. Accepting the new certificate would have changed a fundamental part of the application and could have disrupted competition or encouraged unequal treatment, the panel found.
The decision comes as questions have been raised about the financial eligibility of Íslenskir aðalverktakar, or ÍAV, which won the tender. Its bid was 557 million Icelandic krónur higher than Ístak’s. When the bid was accepted in June, ÍAV had negative equity, despite a tender requirement that bidders have an equity ratio of at least 10 percent.
Fifteen days after the winning bid was announced, ÍAV’s owner forgave 3.3 billion krónur of the company’s debt. The Finance Ministry did not seek information about ÍAV’s financial position during the tender, despite agreeing to provide up to 1.265 billion krónur in additional state equity to Þjóðarhöll ehf.
Finance Minister Daði Már Kristófersson told Morgunblaðið he could not see that the tender process had been flawed. He said he wanted to study the matter further before commenting on ÍAV’s financial eligibility, but did not currently see a reason for a further review of the tender process.
The new National Hall is scheduled to be ready in January 2030.