Kouvola and KSS Energia study removing Ruokokoski dam
Wednesday 25th November 2026 on 07:30 in
Finland
Kouvola and electricity company KSS Energia are considering removing a dam at Ruokokoski and restoring its rapids, Yle reports. The proposal would end production at the small hydropower plant, which is still operating.
The plant, which began operating in 1958, generates about one gigawatt-hour of electricity a year. KSS Energia produces around 600 gigawatt-hours annually in total. One gigawatt-hour is equivalent to the yearly electricity use of about 50 electrically heated detached houses.
The partners are preparing a study, rather than committing to the dam’s removal. It will assess the technical and financial advantages and disadvantages of different options. KSS Energia would take part as the plant’s owner.
The plan is to examine whether the dam can be removed, whether a low dam could be built upstream, and how the rapids could be restored. Kouvola technical director Hannu Tylli said an initial estimate suggests about 150 metres of rapids could be returned to free-flowing conditions. Removing the barrier would also allow fish to move farther upstream.
The study is expected to be completed next spring. It is estimated to cost about 100,000 euros, while the full project could cost around one million euros. Kouvola is seeking state funding and will also explore possible contributions from private individuals, companies, associations and foundations.
The proposal is inspired by restoration work on the Hiitolanjoki River, where three old hydropower dams were removed from the main channel between 2021 and 2023. The river’s final barrier, at the Kurunkoski dam on the Torsajoki tributary, was removed in December 2025. Yle reports that the restoration has allowed landlocked salmon and trout from Lake Ladoga to reach spawning grounds upstream in Finland, and that new salmon fry have already appeared in the restored rapids.
Kouvola’s technical committee is due to decide next Thursday whether the city and KSS Energia should sign an agreement to plan the project in more detail.