Contractor’s error damages Icelandic drugmaker
Friday 27th November 2026 on 23:45 in
Iceland
Icelandic pharmaceutical company Coripharma suffered losses after a contractor severed its power connection during construction on an adjacent plot, leaving the company without electricity for about four hours, mbl.is reported.
The damage occurred during work in Dalshraun, according to utility company HS Veitur. The outage affected several buildings on Reykjavíkurvegur in Hafnarfjörður, including Coripharma. Some businesses had their electricity restored after about an hour.
The outage affected Coripharma’s laboratories, where the company develops generic medicines and conducts chemical analyses and quality tests on raw materials and finished medicines. Research and measurements that were under way when the power failed must be repeated, the company said. The work requires considerable staff time and is costly, but the extent of the damage has not been assessed.
Power was also lost in the company’s staff facilities, while its factory was unaffected. Coripharma employs about 230 people and specialises in developing, manufacturing and exporting generic medicines. Founded in 2018, it took over the former Actavis pharmaceutical factory in Hafnarfjörður.