Court rejects claims over plot left undeveloped for 14 years
Friday 27th November 2026 on 23:01 in
Iceland
Iceland’s Court of Appeal has upheld a ruling in favour of the municipality of Hafnarfjörður in a dispute over the cancellation of a plot allocation after no construction began for 14 years, mbl.is reported.
The 430.6-square-metre plot at Tjarnarvellir 2A, in the Vellir area of Hafnarfjörður, was allocated in 2009 for a hot dog stand. The municipality cancelled the allocation in August 2023, before construction had started.
Tjarnarbúð ehf. sought to have the cancellation overturned or, alternatively, to have the municipality held liable for damages. The company argued, among other things, that the municipality had not treated it equally or acted proportionately.
The plot was created through a change to the local development plan in 2008 and first allocated to Manning ehf. Tjarnarbúð later took over the plot rights. A lease agreement signed in 2013 set a 25-year term, starting on 1 September 2009.
Tjarnarbúð’s current owners acquired the company in 2015. A company representative told the district court that they intended to establish a food business on the plot, but the conditions to begin operating were not in place at the time.
The lease set construction deadlines, including submission of final architectural plans by 1 May 2014 and making the building weather-tight by 1 November 2015. In 2017, Hafnarfjörður extended deadlines for certain commercial plots where construction had not begun. Under the revised terms, Tjarnarbúð had until 4 December 2018 to submit final plans and until 4 June 2020 to make the building weather-tight and level the plot.
The municipality’s letter informing the company of the revised deadlines was sent to its former address. Tjarnarbúð said it did not receive notice of the new deadlines.
In March 2023, the municipality notified the company that the deadlines had passed and construction had not started. It gave Tjarnarbúð until 28 April to submit documents or respond, warning that the allocation could otherwise be cancelled. That letter also went to the former address, and the company said it did not receive it until the deadline had expired.
The municipality extended the response deadline first to 12 May and then to 12 July. No construction plan was submitted. On 24 August 2023, the municipality informed Tjarnarbúð that the allocation had been cancelled, adding that a refund would be made under the law on road construction charges.
Tjarnarbúð argued that the real reason for the cancellation was that the municipality had changed its plans for the area and no longer intended to allow a food business on the plot.