Lieto to dismantle collapsed suspension bridge as investigation continues
Wednesday 25th November 2026 on 18:01 in
Finland
The city of Lieto will begin dismantling the Teilisilta suspension bridge on Friday, after it collapsed on Sunday, Yle reports. Authorities gave the city permission on Wednesday to secure the area, which includes removing the bridge.
The work is expected to take about two weeks. The contractor has been selected without a competitive tender so the dismantling can begin promptly. The contract is worth 49,700 euros.
Eight people were on the bridge when it collapsed in the early evening. Six fell into the Aurajoki River; none suffered serious injuries.
The Safety Investigation Authority and police have examined the scene. The city said the investigation’s findings are expected in several weeks, once the authority completes its report.
The city has previously said that a support cable on one side of the bridge failed, causing it to turn onto its side. Lieto plans to assess a replacement for the bridge before the end of the year, with the matter due to go to decision-makers next year.