Work begins on Sigöldu power station expansion
Tuesday 24th November 2026 on 22:30 in
Iceland
Construction has begun on an expansion of Sigöldu power station, with excavation underway for an enlarged powerhouse, mbl.is reports.
Contractor Ístak is carrying out the work and will build the new structures. The company has set up temporary accommodation and a canteen at the site. Landsvirkjun is preparing its own facilities, which are due to open next year.
Dozens of people are currently working on the project, and the workforce is expected to grow as construction progresses. At its peak, about 140 people may be employed there, according to Gunnar Aron Ólason, Landsvirkjun’s communications officer for new projects.
Sigöldu power station was built about 50 years ago with provision for a future expansion. The project will add a fourth generating unit to the powerhouse and install a new pressure pipe from the plant’s intake to the unit. The discharge channel near the station will also be widened.
The expansion will raise the station’s installed capacity from 150 megawatts to as much as 215 megawatts. Procurement of the generating equipment is in its final stages, with details expected soon.
Electricity generation is expected to continue for most of the construction period. The station will need to stop operating temporarily while work is carried out on the intake and discharge channel. That work is expected to take about four months in 2028.