XTX Markets opens first Kajaani data centre and criticises power delays

Tuesday 24th November 2026 on 10:30 in Finland

data centres, Kajaani, XTX Markets

British trading firm XTX Markets has completed its first data centre in Kajaani, while criticising delays affecting electricity access for its planned expansion, Yle reports.

The company began construction in Kajaani in 2024 and plans to build five data centres along the Kajaani River. Its first facility covers 15,000 square metres and has an electrical capacity of 22.5 megawatts.

XTX uses artificial intelligence and computing models to forecast prices in financial markets. Its algorithms identify and exploit price differences around the world, including differences that last only fractions of a second. The company says it could no longer rent enough computing power from other providers for its needs.

More than 30 full-time staff, including engineers and security and maintenance workers, are based in Kajaani. XTX plans to hire more employees.

The company says it has invested more than 400 million euros in construction in Kajaani, most of it through contracts with Finnish companies. Its second data centre is due to be completed in 2027, and XTX aims to invest billions more.

Electricity supply and grid connections have been secured for the first two data centres, but access for later facilities remains uncertain. XTX says it could build faster if enough electricity were available.

In a company statement, chief operating officer Mike Irwin criticised the slow processing of applications for permits to expropriate land for power lines, saying bureaucracy was hindering the company’s investment plans. “Where permits used to take months, they can now take years,” he said.

XTX trades shares, currencies, bonds, commodities and options on more than 80 marketplaces.

Source 