The operator of a cafe at Tampere’s main library has challenged the city’s tender in Finland’s Market Court, arguing that unclear requirements made the bids impossible to compare fairly, Yle reports.
Kaisa Kalliolahti, whose company Vinedu Oy runs Cafe Metso, filed the appeal in September after losing the contract to Compass Group Finland. The cafe operates under a concession agreement.
The appeal says Compass Group’s bid was exceptionally low and that the company did not provide enough evidence to show it could deliver the required service quality at the prices offered. It also argues that the tender left key product details open to interpretation. For example, it did not specify the size of a bun in meeting packages or how many and what kinds of fruit an assortment should contain.
Tampere asked Compass Group for further information in August because of the low prices. The company said its bid covered all costs and that it could provide the meeting packages at those prices throughout the contract. The city says it had no reason to doubt the offer, adding that the concession agreement places the financial risk on the service provider.
The city also argues that terms such as “small bun or equivalent” and “fruit assortment” are clear enough for industry professionals. No questions about those terms were submitted during the tender process, its response says. The meeting-package prices did not determine the winner, the city adds: Compass Group would have won even if both bidders had received equal points in that category.
Tampere is asking the court to dismiss the appeal and order Kalliolahti to pay the city’s legal costs, which total about 9,500 euros so far.
The tender drew public opposition, and a petition to keep the cafe collected more than 11,000 signatures. The new contract is due to begin on January 1, 2027, if the procurement decision becomes legally binding this year. The court case could delay the start; procurement cases took just under five months on average to be handled by the Market Court in 2025.