SEV completes Sandur power stations for less than estimated

Friday 27th November 2026 on 08:16 in Faroe Islands

energy, infrastructure, SEV

SEV has completed a switching station and battery station in Sandur for 212 million, below the estimated cost of 233 million, KVF reported.

The battery equipment is currently being tested. SEV department manager Jón Nielsen said the project came in under budget because the batteries cost less than expected.

The stations are intended primarily to strengthen and future-proof the electricity grid in Sandoy, where developments include a smolt facility in Skálavík. The project is also part of efforts to reinforce the grid in Suðuroy, where major developments and increased electricity demand are expected.

If a tunnel to Suðuroy is not built soon, SEV says it will begin laying a submarine cable to connect the island’s electricity grid to the grid in the main area.

Source 
(via KVF)