Minister sees no need to review National Arena tender

Wednesday 25th November 2026 on 11:15 in Iceland

Iceland, national arena, public procurement

Finance Minister Daði Már Kristófersson sees no current reason to launch a special review of the tender for construction of the National Arena, but says the ministry is responsible for overseeing the project, mbl.is reports.

He said he wanted to examine the matter further before commenting in detail. Asked whether there had been any procedural failures, Kristófersson said he did not believe so and understood that contractor ÍAV had met the tender’s financial eligibility requirements.

ÍAV’s bid was ISK 557 million higher than Ístak’s, while the overall evaluation scores differed by less than half a point, according to Morgunblaðið. The tender required bidders to have an equity ratio of at least 10%. When ÍAV’s bid was accepted in June, its equity was more than ISK 2 billion in negative territory. The company’s owner later waived ISK 3.3 billion in debt on June 30, 15 days after the award was announced.

The ministry did not obtain information about ÍAV’s financial position as part of the tender process. In written responses to Morgunblaðið, the minister has said it was the responsibility of Þjóðarhöll ehf., the project’s contracting authority, to ensure that bidders met the eligibility requirements.

The state owns 55% of Þjóðarhöll ehf., with Reykjavík City holding the remaining 45%. Asked whether the scale of state funding called for stronger oversight, Kristófersson said the company’s joint ownership affected how the government could act. He added that monitoring the company was the ministry’s responsibility and that it would carry out that role.

On June 5, the minister gave an assurance of up to ISK 1.265 billion in additional state equity for Þjóðarhöll ehf. so it could negotiate with the higher-scoring bidder. Kristófersson said nothing currently indicated that a special examination of the tender was needed.

He said he was placing strong emphasis on improving state procurement. A bill setting out a framework for public investment, modelled on Norway’s, is complete. He said it was long overdue to review the framework, given cost overruns and other shortcomings in public projects, as well as improvements achieved through better processes.