Ministry knew departure station would miss December opening

Saturday 21st November 2026 on 13:31 in Iceland

Iceland, immigration, public services

The Ministry of Justice knew in September that a departure station could not open on December 1 as planned, mbl.is reported. The ministry said it was not safe to begin operating in part of a building while construction continued.

The delay emerged during negotiations with the owners of a building at Klettatröð 8 in Ásbrú. The owners believed part of the building could be used while work continued, but the ministry judged that approach unacceptable for the safety and accommodation of people staying at the station and its staff.

In June, the government construction agency had estimated that permanent premises would not be ready before the summer of 2027. Officials therefore sought temporary accommodation on the Reykjanes peninsula to allow the station to open in December. Fourteen offers from 13 parties were received, but none met the legal requirements without alterations.

The building at Klettatröð 8 was considered the most economical and realistic option. The Ministry of Finance and Economic Affairs authorised negotiations on September 2. On September 16, the day before the first negotiating meeting, Vísir reported that officials were still working towards a December 1 opening.

According to the Justice Ministry, it became clear during the September talks that the station could not begin operating before the end of the year. The ministry’s memorandums were published on the parliament’s website on November 20. That day, a majority of the parliamentary committee on general and education affairs introduced a bill to postpone the station’s opening until December 1, 2027. The one-year delay had been announced on November 11.

The ministry is now aiming to have the station ready in the final quarter of 2027, provided the necessary planning changes are approved. In early October, the ministry said it became clear that members of the Reykjanesbær municipal council might reject the changes and the building permit.

If approval is not secured, the Rockville plot in Suðurnesjabær could be reconsidered. The ministry says a building would have to be constructed there from scratch, making that option slower and more expensive.