Venø’s new electric ferry has been delayed indefinitely after a test at the shipyard found that its motor lacks enough power for the crossing, DR reports.
The ferry was tested on Monday at Hvide Sande Shipyard but was not approved. Its main engine is being replaced with an electric motor, and it should have returned to service on the Limfjord before the start of November.
The crossing from Kleppen, north of Struer, to the island of Venø is just 275 metres long. But the route has strong currents and can have waves that require more power from the motor, said Dennis Jensen, director of technology and culture at Struer Municipality.
Island residents are being served by a loan ferry, with no end date set. The municipality does not yet know when the Venø ferry will make its first voyage under electric power. Jensen said efforts were under way to resolve the problem and that he remained optimistic.
Once the conversion is complete, the ferry will be an electric hybrid. Its electric motor will handle daily operations, while the diesel engines will remain as a backup.