A study of planned pumped-storage plants in Kemijärvi estimates they would support about 100 person-years of employment during construction, but just 6.3 person-years annually afterwards, Yle reported.

Commissioned by the city and funded by the Lapland Regional Council, the study examines the projects’ employment and economic effects. Project manager Mikko Joro said it aimed to clarify issues that had not previously been assessed.

The construction phase is expected to bring about 15 million euros to Kemijärvi. Once the plants are operating, they could increase local business turnover by around 200,000 euros a year, the study says.

Ramboll Finland also assessed alternatives, including battery storage, gas turbines, wind and solar power, and hydrogen and its derivatives. None was found to be an obviously easy option to implement in Kemijärvi’s conditions.

Joro said there had been a national-level message that more balancing power is needed. The need, he said, is not specific to Kemijärvi.

Four pumped-storage plants are planned in the Kemijärvi water system: Ailangan by Kemijoki Oy, Askanaava by Pohjolan Voima, and Räisälä and Kapusta by Suomen Voima. The projects are still at the planning stage and would be significant in scale and impact. They would also be the first of their kind in Finland.

Kemijärvi City Council decided in February not to approve pumped-storage plants in the municipality. The energy companies have continued to advance their projects.