Missing freight trains leave Danish rail problems unresolved until 2027
Monday 16th November 2026 on 05:45 in
Denmark
Train passengers across Denmark face at least two weeks of cancellations and delays from Monday, with no prospect of a lasting solution before spring 2027, DR reports.
Regional trains between Odense and Fredericia will be replaced by buses. Trains from Næstved via Køge Nord to Copenhagen will run only as far as Køge Nord, leading to some cancelled rush-hour services on the Coast Line. On the route between Copenhagen, Køge Nord and Ringsted, and on parts of West Funen, trains will be limited to 80 kilometres per hour.
Banedanmark has found 30 defects on the Copenhagen to Ringsted line that could lead to broken rails. The line is no more than seven years old and cost 10 billion kroner. In August, Banedanmark reported cracks and wear at six points and said the absence of freight trains was a factor: their weight could have ground away defects on the rails.
Freight trains are not expected to use the line until spring 2027, when many will be equipped with the signalling system needed to operate there. Banedanmark said last month that it expects to find similar defects in the meantime.
Steen Thomassen, a commuter representative for the Lille Syd line, doubts that track work will be finished by 29 November, as Banedanmark has announced. He said the underlying cause of the defects had not been resolved and warned that a measurement train run in the spring could reveal problems that force repairs to start again.
DSB communications chief Tony Bispeskov also does not expect normal services to resume on 29 November. He said the planned changes would apply for two weeks, but that normal traffic would not return on that date.
Trains will also continue to face reduced speeds and delays of around five to 10 minutes through Aarup station on Funen, where a technical hut burned down earlier in October.
The disruptions follow a year of repeated problems on Denmark’s rail network, including delays caused by late track work in July, overhead-line problems in June and April, and a signalling fault that halted much of rail traffic in Jutland for two days in January.
DSB statistics show that three out of four journeys between Copenhagen and Odense were on time in September last year, compared with fewer than half in September this year. Banedanmark’s maintenance chief, Nicolai Smidt Sigsgaard, apologised for the current situation and said the remaining defects were being addressed. Bispeskov said the rail network was undergoing extensive construction work, making the additional track defects particularly frustrating.